Clean Energy Siting and Permitting Project (CESP)

CESP Project Update: November 2026

The CESP Draft EIS is available for public comment. Please review and submit any comments before December 11, 2026.

The County will host two open houses for the public to learn more and ask questions about the Draft EIS, see below for more information.

Draft EIS (DEIS)

The Draft EIS (DEIS) is now available and can be viewed and downloaded here:

A hard copy of the Draft EIS is available for review at the Kittitas County Community Development Services office at 411 N. Ruby Street, Suite 2, Ellensburg, WA 98926. Flash drives of the pdf are available upon request.

The Draft EIS evaluates three alternatives for the Clean Energy Siting and Permitting Project:

  • Alternative 1: No Action assumes that energy development for solar, wind, battery energy storage systems (BESS), geothermal, and small modular reactors, would occur with no changes to current county processes.
  • Alternative 2 re-evaluates locations suitable and appropriate for large scale solar and wind facilities along with amending current permitting procedures. Evaluates BESS for significant adverse environmental impacts.
  • Alternative 3 evaluates locations suitable and appropriate for geothermal energy facilities and small modular reactor facilities along with their potential for significant adverse environmental impacts.

DEIS 30-Day Comment Period

Kittitas County welcomes the public, agencies, Tribes, and other interested parties to provide comments on the Draft EIS. The comment period is from November 5, 2026 to December 11, 2026. The comment period will close at 5:00PM on December 11, 2026.

Comments may be emailed to cleanenergy@co.kittitas.wa.us or mailed in at Kittitas County Community Development Services, 411 N. Ruby Street, Suite 2, Ellensburg, WA 98926

Engagement Opportunities

Kittitas County is holding two Draft EIS open houses to gather input from community members on the Clean Energy Siting and Permitting Project.

  1. November 16, 2026, from 5:30PM – 7:30PM at Hal Holmes Community Center
    201 N Ruby Street, Ellensburg, WA 98926
  2. November 21, 2026, from 3:00PM – 5:00PM at UKC Senior Center
    719 E 3rd Street, Cle Elum, WA 98922
This is a key opportunity to provide public comments and learn more about the Kittitas County CESP Project.

CESP Project Video

CESP Project Information

What is the Kittitas County CESP Project?

In February 2026, Kittitas County entered into a contract with the Washington State Department of Commerce to execute a CESP grant awarded in November of 2025. The grant funds a Programmatic Environmental Impact Statement and code update to assist in siting of clean energy facilities within Kittitas County.

Project Goals

The Kittitas County CESP Project goals are to:

  • Determine what energy types are most suitable for permitting,
  • Retain local control of permitting in Kittitas County for identified energy projects,
  • Develop and/or modify county code, where appropriate, so project applicants and the public understand:
    • Where uses may be appropriate,
    • What studies and information are necessary to evaluate applications, and
    • The types of mitigation which may be appropriate for energy projects that are proposed in Kittitas County.
  • Where energy uses may be appropriate, create a streamlined permitting process.

Programmatic Environmental Impact Statement (PEIS)

The Programmatic Environmental Impact Statement consists of a county-wide assessment of alternative energy development and siting standards. The project follows a general EIS process including scoping, stakeholder/public/agency input, development of alternatives and selection of alternatives. The "programmatic" element is because the County is initiating this review without any specific project proposal in mind and with the hopes of providing a framework for alternative energy developers that is predictable, environmentally responsible, and in line with community interests.

The County has hosted scoping open houses and stakeholder meetings, alongside comment periods and multiple public hearings throughout this process. In addition to the PEIS, the County will revisit our alternative energy development regulations to reflect the results of the PEIS. The project is scheduled for completion by June 2027.

Project Process and Schedule

The CESP Project is scheduled to take place over several phases beginning in February 2026 and ending in June 2027.

2026 Project Processs and Schedule

How to Get Involved

Throughout the project, opportunities to learn more and share your input will be posted on the project website and social media.

Key opportunities to share your voice include

  • Attend an open house to learn about the project and share comments,
  • Submit comments online or in writing,
  • Visit our table at community events as the project progresses, and/or
  • Attend public meetings when draft development regulations are released

Additional engagement activities include coordination with agencies, Tribal governments, stakeholders, and regular updates to the Board of County Commissioners.

Project Documents

Draft EIS - CESP DEIS Issuance Notice
Project Kickoff - DS and Scoping Notice
Project Kickoff - Project Charter
Project Kickoff - Project Engagement Plan
Scoping - Fact Sheet
Scoping - Frequently Asked Question
Scoping - Scoping Comment Summary
Scoping - Scoping Comments Index
Scoping - Scoping Comments Master File
Scoping - Scoping Event Summary
Selection of EIS - Community Engagement Progress Report
Selection of EIS - DEIS Summary of Alternatives
Selection of EIS - Preliminary DEIS Progress Report
Selection of EIS - Stakeholders and Tribal Meeting Agenda
Selection of EIS - Stakeholders and Tribal Staff Discussions Summary

Engagement Opportunities

Open House November 16, 2026 530PM - 730PM at Hal Homes Community Center
Open House November 21, 2026 3PM - 5PM at UKC Senior Center


For more information or questions about this project, please call 509-962-7506 or visit the Kittitas County Community Development Services office at 411 N. Ruby, Suite 2, Ellensburg, Washington 98926.

The Clean Energy Siting and Permitting CESP-CLEANENERGY25 RFA is supported with funding from Washington’s Climate Commitment Act. The CCA supports Washington’s climate action efforts by putting cap-and-invest dollars to work reducing climate pollution, creating jobs, and improving public health. Information about the CCA is available at https://climate.wa.gov/